dc.subject |
Àrees temàtiques de la UPC::Edificació::Gestió d'obres |
dc.subject |
Àrees temàtiques de la UPC::Arquitectura::Projectes arquitectònics |
dc.subject |
Railroad stations -- Design and construction |
dc.subject |
Estacions de ferrocarril -- Disseny i construcció |
dc.title |
Organization and management of building-site of central station on high-speed line Madrid-Barcelona French border. |
dc.type |
info:eu-repo/semantics/bachelorThesis |
dc.description.abstract |
The thesis is about the organization and management of a construction site. The
original project is the construction of the Central Station, high-speed line Madrid-
Barcelona-French border.
Because of the magnitude of the work, has been determined to split the building site
into two phases. In a first phase, carrying out the works relating to access to the station
and car park, in a second phase, the works related to the railway station and the
platform.
In the following thesis it will be described all the works previous to the construction of
the central station. That works include the fencing around the construction site, the
implementation of all the facilities necessary for the main works, the construction of the
temporary roads and dimensioning of temporary objects on the building-site.
Furthermore, in the thesis there is list of measurements of the building-site organisation
and a list of mechanisation, equipment and workers and safety regulations.
Finally everything is embodied in the scheme of the building site organisation. |
dc.description.abstract |
Outgoing |